Galena Mining: Reaches construction milestone at Abra mine

Galena Mining Reaches construction milestone at Abra mine

  • Construction is now 75 per cent complete at Galena Mining’s (G1A) 60 per cent-owned Abra Base Metals Mine in Western Australia
  • Processing plant construction activities are 79 per cent complete, concrete civils passing is 95 per cent complete and structural steel passing is 42 per cent complete
  • Galena has also provided guidance for CY23 which is based on the recently updated mine plan, mineral resource estimation and advancing construction
  • The forecast life of mine production now averages 93,000 tonnes per annum of lead metal and 553,000 ounces per annum of silver
  • Shares in Galena are down 18.2 per cent and were trading at 13.5 cents at 1:50 pm AEST
Steve Sam
Steve Sam
Steve Sam is a financial reporter, analyst, and commentator with a strong focus on banking technology, digital payments, and the future of financial services.

You May Also Like

Universal Launches UAE’s First Central Bank Registered Stablecoin

The new digital currency aims to enhance financial transactions in the UAE.Highlights: Universal launched the UAE's first Central...

Mastercard Launches BIN Sponsorship Programme for UK Fintechs

New initiative aims to support fintech innovation in the UK market.Highlights: Mastercard unveils BIN sponsorship programme for UK...

UAE Central Bank Trials Palm Payments, Amazon Abandons Technology

UAE's innovative palm payment trials contrast with Amazon's decision to discontinue similar tech.Highlights: UAE Central Bank begins trials...

Checkout.com Acquires Euro Stablecoin Issuer Blue for Expansion

The acquisition strengthens Checkout.com’s capabilities in the stablecoin market.Highlights: Checkout.com has acquired Blue, a euro stablecoin issuer.The acquisition...