Galena Mining: Expects Abra mine processing plant completion ahead of schedule

Galena Mining Expects Abra mine processing plant completion ahead of schedule

  • Galena Mining (G1A) expects to complete the construction of a processing plant at its Abra base metals mine in Western Australia ahead of schedule
  • Today, the company reported construction progress reached 97 per cent completion as of November 30, and Galena expects practical completion this month
  • Ore is being mined from underground and stockpiled, ready for processing in the new year when concentrate production is also due to begin
  • Considering its “record underground development” in November and commissioning progress to date, G1A believes Abra is “on the verge” of a quick transition into production
  • Company shares are up 13.5 per cent and trading at 21 cents at 3:56 pm AEDT
Steve Sam
Steve Sam
Steve Sam is a financial reporter, analyst, and commentator with a strong focus on banking technology, digital payments, and the future of financial services.

You May Also Like

Why the World’s Wealthiest Are Diversifying Across Borders

London — 18th March 2026 — Global Citizen Solutions (“GCS”), a leading advisory firm in citizenship and residency...

Marquis Software Confirms Data Theft of 672K Bank Customers in Ransomware Attack

The cyberattack raises concerns about data security in the banking sector.Highlights: Marquis Software data breach impacts 672,000 bank...

NCR Strengthens Focus by Offloading Japanese Bank Technology Business to NTT Data

NCR transfers its Japanese banking tech operations to enhance strategic focus.Highlights: NCR sells its Japanese banking technology business...

Agentic Workforce Initiative Enhances Financial Institutions’ Performance

New platform aims to optimize operations for banks and financial service providers.Highlights: New Agentic Workforce initiative launched for...